Archive for Thursday, January 8, 2009

Interchange work set to be finished at the end of February

Crews pour the base for a concrete barrier that will separate traffic along the new interchange at U.S. Highway 24-40 and Kansas Highway 7. The project, which also involved replacing the bridges on K-7 and expanding the lanes on both highways, was scheduled to be completed at the end of 2008, but has been set back and is now scheduled to finish in February.

Crews pour the base for a concrete barrier that will separate traffic along the new interchange at U.S. Highway 24-40 and Kansas Highway 7. The project, which also involved replacing the bridges on K-7 and expanding the lanes on both highways, was scheduled to be completed at the end of 2008, but has been set back and is now scheduled to finish in February.

January 8, 2009

Commuters waiting for the construction along U.S. Highway 24-40 and Kansas Highway 7 to finish will have to wait until the end of February before crews start removing any cones or barricades. Kimberly Qualls, a Kansas Department of Transportation spokeswoman, said the project had been delayed because of “weather and other contractor-related scheduling issues, including work carried over from the 2007 construction season.” The old cloverleaf interchange was scheduled to be replaced with a new, partial cloverleaf or folded diamond interchange by winter 2008. Auxiliary lanes on K-7 and U.S. 24-40 were also part of the construction plan. The lane addition will provide traffic with acceleration and deceleration lanes for the new interchange on- and off-ramps. Qualls said, weather permitting, the project should be completed before March, with the exception of some landscaping work and final touches. She said the cost of the project also had increased since it began in March. The original project was estimated at $35.7 million. Since the start of the project, the cost has gone up to $37.7 million. Qualls said liquidated damages currently were being assessed on APAC Kansas, Inc., the project’s primary contractor, as a result of ongoing construction work that has now extended beyond the scheduled project completion date. She said the damages are being assessed starting from Nov. 15 at $10,000 per day, excluding Sundays and holidays. KDOT official Mike Johnson said crews typically don’t work on Sundays, but they have been working when the weather has been nice so the project can be completed by the new anticipated completion date. Qualls said there still was some construction needed for concrete pavement and concrete barrier, installation of traffic attenuators and signing, removal of temporary striping and placement of permanent striping, and removal of temporary asphalt crossover pavement.

Comments